hammer4reel
08-26-2016, 06:27 PM
Here is the latest release on the dredging of Shark River.
see bottom.
It is scheduled to start Sept 1 prox.
There will be some weekday channel interruptions.
We are also waiting for a "recovery plan" and we are very concerned
that without additional resources $$$ this project will NOT be completed as the bid was originally awarded.
It will be very important the the back channel Spur is fully included.
There is a pumpout station there and it is the source of
high water pollutants especially after a rainfall.
We need the water flushed with the tide changes.
Stay tune for further info. JFD
NOTICE TO MARINERS
Mobile Dredging and Pumping and the New Jersey Department of Transportation Office of Maritime Resources will close a portion of the Shark River channel from September 1, 2016 until on or about September 23, 2016. In accordance with the schedule below.
The portion of the channel to be closed to navigation during dredging operations will be from 40°10'54.20"N, 74° 1'51.05"W to 40°11'6.87"N, 74° 1'53.54"W Monday 9 AM through Thursday 9 PM.
Thursday 9 PM through Monday 9 AM – Channel open but with on-going active dredging operations. During this period mariners are urged to transit at their slowest safe speed, with no wake, and no meeting or passing of other vessels. Mobile Dredging and Pumping may request to enact additional channel closures if the safety of operations cannot be maintained through operational dredging periods.
In addition there will be no Channel Closure on Labor Day. No Channel Closures Permitted 6:00 AM Friday, September 2, 2016 until Noon Tuesday September 6, 2016.
The dredging will be performed by the cutter suction Dredge # D-40 and will be assisted by the vessels WB-24. All pipelines will be marked with buoys and lighted. The dredge and other associated vessels will monitor VHF channels 6, 13 and 16. All mariners should take care to avoid the dredging operations as well as the associated pipelines.
Please include the following additional information in the Notice to Mariners Broadcast “During periods when the channel is open to navigation, mariners are urged to transit at their slowest safe speed to minimize wake and proceed with caution after passing arrangements have been made. Mariners must communicate clearly, and in advance, with the dredge via appropriate VHF channels.”
Mariners should also be advised that State Aids to Navigation (ATON) will be removed for the duration of the project. All mariners, including those utilizing human powered craft, should be especially alert to project pipeline routes and crossings.

hammer4reel
08-26-2016, 06:31 PM
A CONTRACT THAT COST MILLIONS OF $$$$$.
and due to the late start if its not finished by years end it terminates the work being done .
The river needs to be dredged all throughout the channels, not just the ""corner"" as listed in the GPS locations.

and lets just close the river for 4 days out of the week .

seems to me that anyone with half a brain would have set up to do the dredging during the night to not impact the thousand boats that need to pass through the channel .

dales529
08-26-2016, 08:59 PM
Hey Dan. Glad to see you placing in some tournaments as usual. Let me know when anything makes sense LOL. From Fish biomass stock data to beach replenishment to dredging to marine sanctuaries to regulations etc. All fishing advocate groups are up to their eyeballs with minimal support and yet all anyone can do is laugh at the logic or whats the alternative. If there is minimal voice from the public as is the case then they will do what they want when they want with all state and federal approval no matter the party and we don't matter much.
Thanks for posting and caring as always

Foul Hook
08-27-2016, 05:58 AM
Dan, Went to a meeting last night. The former mayor of Neptune was saying this project is caught up in the Transportation Fund mess and wont happen until it is straightened out. I guess we will wait and see.

hammer4reel
08-27-2016, 07:36 AM
Dan, Went to a meeting last night. The former mayor of Neptune was saying this project is caught up in the Transportation Fund mess and wont happen until it is straightened out. I guess we will wait and see.


They havd been gearing up. This project was on hold but is proceeding or they lose the federal funding

Gerry Zagorski
08-27-2016, 07:59 AM
Dan - Not sure this will be the case with Shark River but the same thing happened with Leonardo... Work stalled, Federal money was going to be lost if they did not complete it before 12/31. Wouldn't you know the last few weeks of the year, just before the funds were to be pulled, all this equipment shows up and it gets done.